ARCHITECTURAL DETAILS


Below is a pictorial display.

A 50mm wide damp proof course must be nailed to the batten where the batten contacts the wall framing.
  40mm wide cavity battons offset from building edge 100mm.
 
d
 
d
Installation of flashings were cladding meets stonework and around power box - Note batton offset 100mm
 
Flashing at corner junction
 
d
 
d
Cross section of cavity showing the stainless tie fastened to the timber frame.
 
Stud centre lines must be clearly marked to allow for accurate positioning and cutting of the holes required to enable the installation of the masonry ties back onto the wall framing studs. This can be achieved by using a chalk string
 
d
This image shows the breather / ventilation gap at top of the backing board
 
The temporary nail being removed.
 

 

.